Project:
|
Labuan Coal Power Plant
|
|
Description:
|
Breakwater for coal harbour.
|
|
Location:
|
Labuan, Banten, Indonesia
|
|
Structure Type:
|
Breakwater
|
|
|
Owner:
|
State Electric Company (PLN)
|
|
Engineer:
|
LAPI-ITB
|
|
Contractor:
|
Wijaya Karya (WIKI)
|
|
Project Date:
|
6/2007 - 7/2009
|
|
|
Design Conditions:
|
wave height = 4.1 m
wave period = 12.0 s
structure slope = 1.5H:1V
design water depth = 6.0 m
|
|
|
Armour Layer:
|
Single layer of AJs
C = 3.0 m and C=2.5 m
W = 4.5 tonnes
|
|
|
Underlayer:
| |